Sunet POC Status and Issues
by stefan.josefsson@ipnett.com
Hi
Short POC status and sharing of some documents (POC and Adva DCN)
Regards
Stefan Josefsson
Scope
Juniper Cordoba and Adva FSP3000 R7 POC with Sunet
POC is divided into 2 phases --> this project deals with phase 1 only
1. Lab testing
2. Field testing (Stockholm site to ILA to POP (100km away))
aim: to prove that Juniper's Cordoba solution interworks with ADVA's DWDM on an optical level
Project status short (POC only)
* HW shipped & received and unpacked by Ipnett
* Juniper Cordoba Card received by Sunet and tested by Sunet and Juniper Engineer
Next week
* IPnett will check equipment (fibre & power it up)
* Functionality tests at IPnett's premises with ADVA engineer on 2nd Nov
* HW transport and installation at Sunet on 3rd Nov
* POC will be done with onsite ADVA engineer & IPnett & remote Juniper engineer from 4th to 6th Nov
Attachments
Updated Test Plan,
technical documentation
Configuration Plan
Issues
* Test review and plan Update
Adva update from Michal based on latest feedback provided on initial review call (documentation attached)
* Functionality tests at IPNett's premises
Ipnett planned to fully fibre up & configure the test set at IPnett's premises on Monday with Michal from ADVA
* Cabling Plan
Attached to MoMs "2015-10-14.05 SUNET OR30432841"
* DCN design planning for roll-out
* Sunet Comments/questions/requirements translated and sent to ADVA
* Request to Adva for dedicated team for DCN planning to address specific requirements from by Sunet
* Adva technical documetation enclosed, "Preparation for GMPLS Service Manager", "Control Plane"
.