Hi
Short POC status and sharing of some documents (POC and Adva DCN)
Regards
Stefan Josefsson
Scope
Juniper Cordoba and Adva FSP3000 R7 POC with Sunet
POC is divided into 2 phases --> this project deals with phase 1 only
1. Lab testing
2. Field testing (Stockholm site to ILA to POP (100km away))
aim: to prove that Juniper's Cordoba solution interworks with ADVA's DWDM on an
optical level
Project status short (POC only)
* HW shipped & received and unpacked by Ipnett
* Juniper Cordoba Card received by Sunet and tested by Sunet and Juniper Engineer
Next week
* IPnett will check equipment (fibre & power it up)
* Functionality tests at IPnett's premises with ADVA engineer on 2nd Nov
* HW transport and installation at Sunet on 3rd Nov
* POC will be done with onsite ADVA engineer & IPnett & remote Juniper
engineer from 4th to 6th Nov
Attachments
Updated Test Plan,
technical documentation
Configuration Plan
Issues
* Test review and plan Update
Adva update from Michal based on latest feedback provided on initial review call
(documentation attached)
* Functionality tests at IPNett's premises
Ipnett planned to fully fibre up & configure the test set at IPnett's premises on
Monday with Michal from ADVA
* Cabling Plan
Attached to MoMs "2015-10-14.05 SUNET OR30432841"
* DCN design planning for roll-out
* Sunet Comments/questions/requirements translated and sent to ADVA
* Request to Adva for dedicated team for DCN planning to address specific
requirements from by Sunet
* Adva technical documetation enclosed, "Preparation for GMPLS Service
Manager", "Control Plane"
.