On Thu, 11 Aug 2016, Kurosh Bozorgebrahimi wrote:
Hello,
an update from our side.
1. Our Sodankylä router has been arrived and we are about to ship it to
Sodankylä next week. Should be online before the September 1 deadline.
2. Sodankylä - Luleå 10G wave has been ready for months. We will
connect it at Sodankylä when our router will be installed. The Luleå
end is more complicated, we basically have options to send our field
engineer to the site or, if possible, to ask some local (SUNET?) people
help with the patching between our DWDM and NORDUnet router. Lars, do
you know if it's possible to ask SUNET help for that? Our DWDM has an
LR optic installed at the port.
3. Our DWDM relocation at Luleå has stalled, we have not got any
feedback from the fiber provider (DNA) about rerouting our fiber to the
new SUNET site. We are still pushing that option, but most probably it
will not happen before September 1.
4. Telia 10G wave installations are scheduled for August 29 according to
my knowledge. We gave Utsjoki patching instructions we got from you to
the subcontractor (Relacom).
4- Installation of routers in Utsjok will happen
on Wednesday
August 31. I will be there and do this job. The Finland Telia-cabin
is 100 meters away from our node. Janne, do you know is it possible
to visit Telia site and who should we contact if we face some problem
regarding connection over the boarder?
Janne is currently on vacation and will back August 29. He has done all
the communication between us and Telia, so don't know, but I will try to
figure out that...
BR, Jani