Dear All
Please see the notification below which was sent by the EC on Monday.
For convenience all the related documentation to the notification is attached.
All partners costs have been accepted, and the EC is paying out the maximum interim payment allowable (10% of the
total grant).
Based on this we have today informed our PO that we have no observations and asked him to check when we could expect
the interim payment.
Our PO indicated that “soon“ as written in the letter, usually means 30 days from the dated letter, i.e., in our
case around 31 July or shortly thereafter.
I will share with you in a separate email the calculated interim payments for you to check, and also ask you to start
preparing/confirming the required banking information.
This so your respective payments can be made without undue delay once the interim payment is received at LNU.
Best regards
Shamim
-------------------------------------------------
Shamim Patel (ACA)
Project Manager | Exten.(D.T.)2 Project
Linnæus University
Office of External Relations
SE-351 95 Växjö | Sweden
M: +46 (0)705 898396 | lnu.se
-------------------------------------------------
From:
European Commission <EC-NO-REPLY-GRANT-MANAGEMENT@nomail.ec.europa.eu>
Date: Monday, 1 July 2024 at 14:05
To: Shamim Patel <shamim.patel@lnu.se>
Subject: For Action - Exten.D.T.2 - 101060231 - REP-101060231-1 - Reporting and payment letter
|