Dear All
Marcelo and I had a meeting with Angel, our PO, this afternoon and checked with him your queries on deliverables:
-
It is OK to shift D1.2 Initial Data Management Plan from M6 to M8.
-
When does a deliverable become public?:
-
A deliverable will only become publicly available on EU websites when formally approved by the PO.
-
Some POs formally approve the deliverables themselves, others prefer to leave the formal approval until the reviewers at the periodic reporting stage have reviewed
them too.
-
Any EU partner can log in and check on the portal to see the status of their deliverable, including whether it has been approved:
<Log in>Click on <ExtenD.T.2 Project: Actions><Manage Projects><Continuous Reporting><Deliverables>
-
There are no fixed rules on when we ourselves can disseminate/publish our public deliverables e.g., on our extendt2 website after they have been submitted.
-
Angel does not see an issue if we decide ourselves whenever to do this.
-
However, Angel asked that we inform him, if we would like any deliverables to be formally approved by him on the portal, to alleviate any doubt.
-
He will usually, unless he is absent, review (and approve (or not)) our deliverables usually within a day or two of request.
-
What is the procedure if a deliverable is submitted/uploaded on time and then we wish to replace it in the next week or two with a higher quality version or a
small adjustment to a table etc.
-
Angle was not sure. We MAY be able to resubmit IF he has not approved or rejected the deliverable.
-
However, he prefers that he be contacted, as he does see an issue of us replacing a deliverable in such circumstances. He can reject the deliverable from his
side then and allow us to resubmit/upload a new version without issue.
Best regards to you all for the w/e!
Shamim